We believe our true measure of success is a satisfied client. That is why we believe that "Every project is a self portrait of those who built it. Therefore we should autograph our work with quality and integrity.
From the RAM Development Team:
1/7
FLORIDA A&M UNIVERSITY BRAGG STADIUM REPAIRS
This project consisted of repairs to sixty-four steel and concrete columns to Column Row A in Bragg Stadium. This included removing and replacing sixteen sets of stairs and handrails. New stairs were fabricated offsite, painted, then installed. The project also included miscellaneous painting, storm drain repairs, and removal and replacement of plumbing and electrical to allow welders to have better access.
Project Cost: $390,968 Completion: May 2018
Owner: Florida A&M University Architect: Barkley Consulting Engineers