In 2016, RAM built a new PEMB gymnasium at the Ghazvini Learning Center. The project included extensive sitework, a new cast-in-place concrete slab, brick exterior, aluminum canopy, new ceramic tile bathrooms, HVAC with duct-mounted smoke detectors, and mounting of 36 light fixtures and gymnasium equipment.

Total Project Cost: $1,794,000     Project Size: 12,664 SF     Completion: December 2016

Owner: Leon County Schools    Architect: JRA Architects, Inc.